Hard Rock was one of the first crews on the Rayos Del Solar project scene that kicked off in November 2020, in southern Cameron County, Texas, near La Feria. The $91-million, 180-megawatt solar power plant will be one of the largest solar farms in the United States when completed in the first half of 2022.
Before a single pile was driven and solar panel installed, Hard Rock’s crews were onsite to complete approximately 20,000 feet of bores across the 2,000-acre plot of land.
“Like on oil and gas projects, what can’t be open-cut because of environmental concerns or existing aboveground infrastructure gets drilled,” explained Seago. “HDD was used to install electrical conduit under every river, creek, waterway, road and pipeline.”
In total, Hard Rock completed 88 drill shots; most were 330 feet or under, but almost a dozen exceeded 850 feet. Bores were designed in a rectangular pattern and usually included between four and five shots next to each other to support the rows of panels that would later be installed.
HDD work was one of the first phases of the job – even before trenching crews. Drill crews bored using GPS entry and exit points and pulled back 8-inch PVC fusible pipe. The trenching crews directly burying electrical lines in less sensitive areas would trench up to the entry points of the bores, pull the cables through and keep going.
While the bores were completed in rural areas, Seago said there were existing utilities that needed to be located before boring could begin.
“It may look like nothing’s out there, but we did spend time with our vacuum excavators potholing a few electrical and fiber lines, as well as pipelines that also pass through the area,” he said. “Once those lines were identified, we could get to work.”
Hard Rock crews used the D40x55 S3 rigs to complete all the bores, and Baker said it’s the ideal machine for the ground conditions and the distances they were drilling. “We know how challenging and ever-changing soils can be in this part of Texas,” he explained. “While the crews didn’t encounter a lot of rock, the area’s sticky clay also needed to be accounted for.”
Fluids run included a mixture of bentonite, a dispersant additive to help prevent clay particles from sticking to tooling, and an additive to help control clay swelling. Seago said crews went heavy on the flow, but the volume of fluid didn’t warrant bringing in a mud recycling system. Instead, crews used their 800-gallon vacs to remove spoils and disposed the spoils at a designated site that the EPC contractor established.